Gas Pipeline · DEPL · 2023

Client
DEPL
Year
2023
Route length
18 km
Location
Maharashtra
State
Maharashtra
Service
Gas Pipeline

Project overview

City Gas MDPE Pipeline – Maharashtra was delivered for DEPL in 2023, covering a route of 18 km in Maharashtra.

Scope

  • MDPE gas pipeline
  • HDD crossings and hydro testing